Fabrication & Installation of Piping, Support, Steel Structure and LPG Tank Pump Column – South Pars Phases 22,23&24 |
|
Client: |
Panahsaz Iran Engineering Co. |
Start Date: |
Oct, 2013 |
Status: |
Ongoing |
Work Volume: |
Fabrication and Installation 88000 ID Piping + Fabrication and Installation 38000 kg Support + Fabrication and Installation 180000 kg Steel Structure + Fabrication and Installation of LPG Tanks Pump Column |
Contract Total Amount: |
50 Billion Rials |
Description: |
Fabrication &Installation of Piping and Support, Test Package Preparation ,Line Check ,Hydro test, Flushing ,Reinstatement ,Fabrication and Installation of Steel Structure, Fabrication and Installation of LPG Tanks Pump Column from Start to Pre-Commissioning |