Fabrication & Installation of Piping, Support, Steel Structure and LPG Tank Pump Column – South Pars Phase 19

 

Fabrication & Installation of Piping, Support, Steel Structure and LPG Tank Pump Column – South Pars Phase 19

Client:

Panahsaz Iran Engineering Co.

Start Date:

May, 2014

Status:

Ongoing

Work Volume:

Fabrication and Installation 90000 ID Piping + Fabrication and Installation 25000 kg Support +  Fabrication and Installation 160000 kg Steel Structure + Fabrication and Installation of LPG Tanks Pump Column

Contract Total Amount:

52 Billion Rials

Description:

Fabrication &Installation of Piping and Support, Test Package Preparation ,Line Check ,Hydro test, Flushing ,Reinstatement ,Fabrication and Installation of Steel Structure, Fabrication and Installation of LPG Tanks Pump Column from Start to Pre-Commissioning