Fabrication & Installation of Piping, Support &Scaffolding and Equipment Installation Area 3 – South Pars Phases 17 & 18 |
|
Client: |
Panahsaz Iran Engineering Co. |
Start Date: |
Aug, 2009 |
Status: |
Completion of the project |
Work Volume: |
Fabrication and Installation 125000 ID Piping + Fabrication and Installation 110000 kg Support + 52000 m² Scaffolding + 4000000 kg Rotary ,Fixed Equipment Installation |
Contract Total Amount: |
18 Billion Rials |
Description: |
Fabrication &Installation of Piping and Support, Test Package Preparation ,Line Check ,Hydro test, Flushing ,Reinstatement ,Scaffolding and Rotary ,Fixed Equipment Installation from Start to Pre-Commissioning |