Fabrication & Installation of Piping, Support, Steel Structure and LPG Tank Pump Column – South Pars Phases 15 & 16

Client:

Panahsaz Iran Engineering Co.

Start Date:

Jan, 2010

Status:

Completion of the project

Work Volume:

Fabrication and Installation 90000 ID Piping + Fabrication and Installation 45000 kg Support + Fabrication and Installation 173000 kg Steel Structure + Fabrication and Installation of LPG Tanks Pump Column

Contract Total Amount:

36 Billion Rials

Description:

Fabrication &Installation of Piping and Support, Test Package Preparation ,Line Check ,Hydro test, Flushing ,Reinstatement ,Fabrication and Installation of Steel Structure, Fabrication and Installation of LPG Tanks Pump Column from Start to Pre-Commissioning

 

 

Fabrication & Installation of Piping, Support, Steel Structure and LPG Tank Pump Column – South Pars Phases 22,23&24

Client:

Panahsaz Iran Engineering Co.

Start Date:

Oct, 2013

Status:

Ongoing

Work Volume:

Fabrication and Installation 88000 ID Piping + Fabrication and Installation 38000 kg Support +  Fabrication and Installation 180000 kg Steel Structure + Fabrication and Installation of LPG Tanks Pump Column

Contract Total Amount:

50 Billion Rials

Description:

Fabrication &Installation of Piping and Support, Test Package Preparation ,Line Check ,Hydro test, Flushing ,Reinstatement ,Fabrication and Installation of Steel Structure, Fabrication and Installation of LPG Tanks Pump Column from Start to Pre-Commissioning

 

Fabrication & Installation of Piping, Support and Steam Tracing System – South Pars Phases 9 & 10

Client:

Gamma Engineering Co.

Start Date:

Jun, 2006

Status:

Completion of the project

Work Volume:

Fabrication and Installation 37000 ID Piping + Fabrication and Installation 10000 kg Support + Steam Tracing System

Contract Total Amount:

6 Billion Rials

Description:

Fabrication & Installation of Piping and Support , Installation of Steam Tracing System , Test Package Preparation ,Line Check ,Hydro test, Flushing ,Reinstatement from Start to Pre-Commissioning

Fabrication & Installation of Piping, Support, Steel Structure and LPG Tank Pump Column and Equipment Installation – South Pars Phases 9 & 10

Client:

Panahsaz Iran Engineering Co.

Start Date:

Dec, 2007

Status:

Completion of the project

Work Volume:

Fabrication and Installation 48000 ID Piping + Fabrication and Installation 35000 kg Support +  Fabrication and Installation 150000 kg Steel Structure + 96000 kg Rotary ,Fixed Equipment Installation + Fabrication and Installation of LPG Tanks Pump Column

Contract Total Amount:

  1. 8 Billion Rials

Description:

Fabrication & Installation of Piping and Support, Test Package Preparation ,Line Check ,Hydro test, Flushing ,Reinstatement ,Fabrication and Installation of Steel Structure, Rotary &FixedEquipment Installation,  Fabrication and Installation of LPG Tanks Pump Column from Start to Pre-Commissioning

Fabrication & Installation of Piping and Support Area 3 – South Pars Phases 9 & 10

Client:

Dor Riz Technical & Engineering Co.

Start Date:

Aug, 2008

Status:

Completion of the project

Work Volume:

Fabrication and Installation 60000 ID Piping + Fabrication and Installation 45000 kg Support

Contract Total Amount:

  1. 3 Billion Rials

Description:

Fabrication &Installation of Piping and Support, Test Package Preparation ,Line Check ,Hydro test, Flushing ,Reinstatement  from Start to Pre-Commissioning

Fabrication & Installation of Piping, Support &Scaffolding and Equipment Installation Area 3 – South Pars Phases 17 & 18

Client:

Panahsaz Iran Engineering Co.

Start Date:

Aug, 2009

Status:

Completion of the project

Work Volume:

Fabrication and Installation 125000 ID Piping + Fabrication and Installation 110000 kg Support +  52000 m² Scaffolding + 4000000 kg Rotary ,Fixed Equipment Installation

Contract Total Amount:

18 Billion Rials

Description:

Fabrication &Installation of Piping and Support, Test Package Preparation ,Line Check ,Hydro test, Flushing ,Reinstatement ,Scaffolding and Rotary ,Fixed Equipment Installation from Start to Pre-Commissioning

 

Fabrication & Installation of Piping, Support, Steel Structure and LPG Tank Pump Column – South Pars Phases 17 & 18

Client:

Panahsaz Iran Engineering Co.

Start Date:

Aug, 2009

Status:

Completion of the project

Work Volume:

Fabrication and Installation 89000 ID Piping + Fabrication and Installation 43000 kg Support +  Fabrication and Installation 170000 kg Steel Structure + Fabrication and Installation ofLPG Tanks Pump Column

Contract Total Amount:

30 Billion Rials

Description:

Fabrication &Installation of Piping and Support, Test Package Preparation ,Line Check ,Hydro test, Flushing ,Reinstatement ,Fabrication and Installation of Steel Structure, Fabrication and Installation of LPG Tanks Pump Column from Start to Pre-Commissioning

 

Fabrication & Installation of Piping, Support & Scaffolding and Equipment Installation Area 5 & 6  – South Pars Phases 17 & 18

Client:

Panahsaz Iran Engineering Co.

Start Date:

Aug, 2010

Status:

Completion of the project

Work Volume:

Fabrication and Installation 420000 ID Piping + Fabrication and Installation 350000 kg Support +  80000 m² Scaffolding + 6500000 kg Rotary ,Fixed Equipment Installation

Contract Total Amount:

100 Billion Rials

Description:

Fabrication &Installation of Piping and Support, Test Package Preparation ,Line Check ,Hydro test, Flushing ,Reinstatement ,Scaffolding and Rotary ,Fixed Equipment Installation from Start to Pre-Commissioning

 

Piping Fabrication (Shop Fabrication) of Units 100 ,103 ,109 ,110 ,122 ,143 ,160 ,181 & 185 – South Pars Phase 19

Client:

Dor Riz Technical & Engineering Co.

Start Date:

Jul, 2012

Status:

Completion of the project

Work Volume:

150000 ID Piping Fabrication (Shop Fabrication)

Contract Total Amount:

29 Billion Rials

Description:

Material Delivery ,Cutting ,Beveling ,Fabrication ,Welding ,NDT & PWHT Release ,Spool Release of Piping

Piping & Support Installation of Units 103 & 160 – South Pars Phase 19

Client:

Dor Riz Technical & Engineering Co.

Start Date:

Jul, 2012

Status:

Ongoing

Work Volume:

145000 ID Piping Installation + 970000 kg Support Installation

Contract Total Amount:

102 Billion Rials

Description

Installation & Welding of Piping and Support, Test Package Preparation ,Line Check ,Hydro test ,Flushing ,Reinstatement ,As built and Final Document

شرکت ساتراپ کشت و صنعت پارسیان

زمینه فعالیت :تولید و توزیع کشاورزی -باغداری -گلخانه-زنبورداری-پرورش و تکثیر انواع طیور و آبزیان-کشت گیاهان دارویی-کشت انواع حبوبات و دانه ها-پرورش احشام و انواع و اقسام چهارپایان-صنایع بسته بندی-ساخت و تولید قطعات صنعتی کشاورزی-صادرات و واردات کلیه کالاهای مجاز بازرگانی

 

دسترسی سریع

آماربازدیدازسایت ما

امروز 7

دیروز 1

این هفته 41

این ماه 48

کل بازدید 8870